Work Permits

Public view of all work permits - 26-Oct-2026

346
Total
0
Identified
3
Planned
7
In Progress
336
Completed
104
Approved
# Date Location Activity Equipment Permit Type Status Agency Supervisor Version Actions
#354 27-Oct-2026 UNIT 1 U1 12 wk pressure setting WB ONLY PTW PLANNED BMC PP-MUNESHWAR NAVIN DHARANI BRAHMA
6000329854
v1
#353 27-Oct-2026 UNIT 3 4 wkly pm job U3 Group B WB ONLY PTW PLANNED BMC PP-MUNESHWAR NAVIN DHARANI BRAHMA
6000329854
v1
#352 27-Oct-2026 UNIT 1 Welder test in ID fan sto WELDING TEST ONLY LWC PLANNED BMC PP-MUNESHWAR NAVIN DHARANI BRAHMA
6000329854
v1
#350 24-Oct-2026 UNIT 1 U#1 SB 100% LINE MANUAL V SB LINE ONLY PTW INPROGRESS BMC PP-MUNESHWAR NAVIN DHARANI BRAHMA
9161724095
v2
#348 24-Oct-2026 UNIT 1 U#1SB MOV SB-06,SB-07 VAL VALVE ONLY PTW INPROGRESS BMC PP-MUNESHWAR NAVIN DHARANI BRAHMA
9161724095
v3
#344 24-Oct-2026 UNIT 2 U2 MILL C BIG CR2 APPROAC MILL LWC HOT AND HEIGHT WORK INPROGRESS BMC PP-MUNESHWAR NAVIN DHARANI BRAHMA
9161724095
v3
#342 24-Oct-2026 U3 U3 AIR PIPELINE LAYING AT BOILER LWC HOT WORK INPROGRESS BMC PP-MUNESHWAR NAVIN DHARANI BRAHMA
9161724095
v3
#339 24-Oct-2026 UNIT 2 U2 Burner Area Insulation BURNER LWC HEIGHT WORK INPROGRESS INSULATION-DEEPAK CNSTRUCTION SWARUP
6000329854
v7
#331 21-Oct-2026 UNIT 3 U3 BOILER 10 M TO 37 M PA BOILER STRUCTURE LWC HEIGHT WORK INPROGRESS PAINTING-SAMIYA ENGG HASIM ALI
9161724095
v2
#330 21-Oct-2026 UNIT 3 SPARE BURNER SERVICING & BURNER ONLY LWC INPROGRESS BMC PP-MUNESHWAR NAVIN DHARANI BRAHMA
6000329854
v2