Work Permits

Public view of all work permits - 28-Jul-2026

14
Total
0
Identified
5
Planned
6
In Progress
3
Completed
8
Approved
# Date Location Activity Equipment Permit Type Status Agency Supervisor Version Actions
#17 28-Jul-2026 UNIT 3 U3 GROUP-A WB PRESSURE SE BOILER WB ONLY PTW PLANNED BMC PP-MUNESHWAR NAVIN DHARANI BRAHMA
6386612174
v2
#16 28-Jul-2026 UNIT 1 U1 60m scrap cutting BOILER STRUCTURE LWC HOT AND HEIGHT WORK PLANNED SCRAP CUTTING-TECHNO HITECH Dibakar saha
8638434841
v1
#15 28-Jul-2026 UNIT 1 8 wk pm of LDO Pressuring LDO Pump ONLY PTW PLANNED BMC PP-MUNESHWAR NAVIN DHARANI BRAHMA
6386612174
v4
#14 28-Jul-2026 UNIT 3 U3 40-50m Boiler Painting BOILER STRUCTURE LWC HEIGHT WORK PLANNED PAINTING-SAMIYA ENGG TAUHIL ALAM
6386612174
v1
#13 28-Jul-2026 UNIT 3 U3 50-60m Boiler Painting BOILER PENT HOUSE LWC HEIGHT WORK PLANNED PAINTING-SAMIYA ENGG TAUHIL ALAM
6386612174
v3
#12 27-Jul-2026 UNIT 2 Unit 2 Sofa cor 2 dmpr de Boiler Sofa ONLY LWC INPROGRESS BMC PP-MUNESHWAR NAVIN DHARANI BRAHMA
9707149828
v3
#11 27-Jul-2026 UNIT 1 U1 12wk Pressure setting BOILER ONLY LWC INPROGRESS BMC PP-MUNESHWAR NAVIN DHARANI BRAHMA
9707149828
v8
#7 21-Jul-2026 UNIT 3 U3 0-10m boiler Painting Boiler LWC HEIGHT WORK INPROGRESS PAINTING-SAMIYA ENGG TAUHIL ALAM
6386612174
v2
#6 21-Jul-2026 UNIT 3 U3 16m win box bottom R&L BOILER LWC HEIGHT WORK INPROGRESS INSULATION-DEEPAK CNSTRUCTION SWARUP
6000329854
v1
#5 25-Jul-2026 UNIT 1 U1 Boiler 13m Platform st Boiler LWC HOT AND HEIGHT WORK INPROGRESS FABRICATION-JAGAT BRAHMA VIMAL DAS
8135958304
v1
#4 25-Jul-2026 UNIT 1 U1 60m scrap cutting Boiler LWC HOT AND HEIGHT WORK INPROGRESS SCRAP CUTTING-TECHNO HITECH Dibakar saha
8638434841
v3